Benalmádena extends deadline for panoramic lift refurbishment until November 2026
According to a technical report, the extension has been prompted by a 34-day delay in the delivery of the new lift equipment by the manufacturer, as well as the fact that certain stages of the installation cannot be carried out simultaneously